current activities


FIELD WORK
   
1 / 7
2 / 7
3 / 7
4 / 7
5 / 7
6 / 7
7 / 7

COCHITI LAKE RANGE LINE SURVEY- 2017

William J. Miller Engineer’s Inc. assisted Wolf Engineering with the survey of eleven sediment range lines in White Rock Canyon above Cochiti Lake.  This work contributes the ongoing effort of the Corps of Engineers, Albuquerque District, to monitor sediment inflow and accumulation to Cochiti Lake.  This is the sixth consecutive year that crews from these two companies have surveyed theses range lines for the Corps of Engineers.  The survey was conducted during the August 29-31, 2017 period.  The survey crews were supported by Far Flung Adventures guide service.

 

 


   
1 / 2
2 / 2

POJOAQUE BASIN REGIONAL WATER SYSTEM- PHASE II GEOTECHNICAL INVESTIGATION - 2017

William J. Miller Engineers, along with Southwest Water Design partner Wolf Engineering, has received a contract from the Bureau of Reclamation, Albuquerque Area Office, for the collection of geotechnical data required for the design of features of the Pojoaque Basin Regional Water System. Field data collection and laboratory testing is performed by Western Technologies, Inc. of Albuquerque, who drilled approximately 2,500 feet of borehole and excavated approximately thirty test pits along the alignment of the proposed water supply project pipeline and ancillary facilities.

 

 

completed projects

Water Resource Management

Project Name: Phase I - Archibeque Ditch Diversion Structure Rehabilitation and Pipeline

Client: Archibeque Ditch Association

Completion Date: February 16, 2018

William J. Miller Engineers prepared the design plans and specifications for the Archibeque Ditch Diversion Structure Rehabilitation and Pipeline Project. The structure project work consisted of the excavation and removal of vegetation, the installation of a boulder cross vane on the Rio Puerco, a new steel irrigation heading structure with 18” diameter headgates. The pipeline project work included the excavation and backfill for the installation of 5,863 linear feet of PVC pipe.

Project Name: Acequia Mesa Del Medio

Client: Acequia Mesa Del Medio

Completion Date: April 26, 2018

William J. Miller Engineers prepared the design plans and specifications for the Acequia Mesa Del Medio. The project work included the fabrication, excavation, installation, and backfill for twenty-six single lateral gate compuerta structures, four double lateral gate compuerta structures, thirty stop gates, thirty-four 18" diameter slide gates, one hundred seventy linear feet of 18" diameter pipe, two hundred ten cubic yards of rip-rap ditch stabilization and the installation of 30" diameter HDPE irrigation pipe as well as a 30" Corrugated Metal Pipe.

   

featured projects

Flume Rehabilitation
River Rehabilitation
Acequia Rehabilitation

ACEQUIA RAINSVILLE NORTE FLUME

ACEQUIA DEL LLANO NAMBE

SAN AUGUSTINE COMMUNITY DITCH